Projects: Railroad Utilities

Lakeridge & 407

CP Rail

Rogers FOC was exposed, relocated north and placed in split steel on grade temporarily until the new rail bridge was built. ‎Once the bridge was built, brackets and 4" trough was installed on the bridge span. The split steel was then removed and the cable was placed into the trough.